Installing the CLU


The maximum acceptable difference of level between the CLU and the CSM (EPU + SCU/MMU) of the DPS 9000/8xx is one metre.

The CLU should be installed no further than 3 metres from the connecting pieces of the pipes which are necessary, at the customer end, to supply the chilled water, Bull supplies hoses of this length for connecting these connecting pieces to the CLU.

 

Help0018.gif (6819 bytes)

Cooling System Skeleton Diagram

The CSM element and the CLU are connected by 30-metre hoses.