CDR Recovery Job Summary Report

About Example

Sample Report

 

CDR Recovery Job Summary Report

Report X.X.0 generated on yyyy/mm/dd hh:mm:ss
CommCell ID : F5742
CommCell : sogo2

-- Report Criteria --
  • Group By: None
  • Job Status: All
  • Include: Failure Reason
  • Computers: All
     
  • Agent Types: All
  • Last 24 Days

    Summary
    Total Jobs Successful Unsuccessful Running Total Size Start Time End Time
    1 1 0 0 79.79 KB 12/18/2008 14:37:22 12/18/2008 14:38:49


    Job ID (Status) Client (Source/Destination) Agent Start Time End Time or Current Phase Duration Size Initiating User

    60

    olympus/athena ContinuousDataReplicator 12/18/2008 14:37:22 12/18/2008 14:38:49 0:01:27 79.79 KB cvadmin



     


  • Notes: ~
  • ~~*~ Scheduled jobs ~
  • ~~1~ Restore With 1-Touch ~
  • ~Job status:C - Completed; CWE - Completed with errors; K - Killed; F - Failed ~
  • ~Color based on job status:  
    Active Delayed Completed Completed with errors Killed Failed